Tuesday, August 13, 2013

Update from Atlanta Gas Light

Marci Davis of Atlanta Gas Light contacted MANA president Bev Monroe with updates on the project that has been going on in the neighborhood since last September:

As neighbors have noticed, work has started up again in the easement by Wood Trail.  The section between Lawrenceville Hwy and Wood Trail is being re-done to go under the creek beds.  Pipes we see lying on the ground by Wood Trail are not there permanently.

As to the area between Wood Trail and Hunting Valley, they have to go back in over the next few months to make sure everything is as it should be. They may have to bring the big drill rigs back in. Property owners adjacent to the easement have been contacted and AGL is working with them.  Some of the work will be completed in the next couple of months, and monitoring of project quality will be ongoing into early next year.

People can contact AGL about the project at either the hotline number, 404-584-3130, or at eastsidepipeline@aglresources.com.